Home/ Cases/ Power & Energy/ Fort Projects Private Limited
Liquidation — order passed IN PROCESS

Fort Projects Private Limited

Corporate insolvency — liquidation in process · source: NCLT order, 20 Jun 2025

Sector Power & Energy Bench NCLT Kolkata Last process activity 9 months ago · claims re-verified

Case record

at a glance

Admitted by the Kolkata bench on a petition by a financial creditor. Current status: Liquidation.

Admission to liquidation order
1 yr 7 mo
This case
NCLT Kolkata median · 11 mo
All India median · 1 yr 1 mo
Medians: time from admission to a liquidation order, over closed cases (n = 337 / 3,069). Pre-packs left out.
The company
Private limited company in Power & Energy, registered in West Bengal
Admitted claims
₹10–100 Cr
Where the process stands
Admitted→Liquidation ordered
How cases like this ended
Power & Energy · 204 closed
Resolved 29% · Liquidation 48% · Withdrawn or closed 23%
NCLT Kolkata · 727 closed
Resolved 25% · Liquidation 49% · Withdrawn or closed 27%
Resolved cases in this sector: creditors' typical haircut 82.1% n=57
Liquidations in this sector: typical recovery 4.7% of claims n=37
Subscriber access

Full case intelligence is gated

This page's financial detail is available to stressed.in subscribers — for ARCs, PE funds and resolution professionals.

7 sections of this case are locked.

Admitted claims & creditor classesCommittee of creditorsCompany & MCA recordTimeline & key dates · 5 tribunal ordersProfessionalsBenchmarks against this caseIntelligence note
See plans →
Sources, basis and disclaimers → ·
report an error